Foundations Built for Monument Signage

Pooler Collage 2Pooler Collage 12-20-13

Onsite, our crews are busy completing work at the major retailers and framing at many future retail spots.

  • Petsmart is getting the finishing touches. Exterior signage has been installed and interior fixtures are being placed.
  • Michael’s electrical panel is now in progress. EIFS is complete, as well as exterior stairs, the gas meter and bollards.
  • Ross Dress for Less now has completed EIFS. Our team installed the interior grid, and sales floor lighting is in progress.
  • T.J. Maxx crews are installing spiral duct, EIFS and framing back of house walls continues.
  • Hibbett Sports and Rack Room Shoes are seeing interior progress as well.

We completed paving in the parking lot, and striping is in progress. Foundations for signage are in progress.

Tilt-Up Walls Continue to Rise

Pooler Collage 10-4-13

Work is progressing nicely across the entire site on Pooler Parkway. Our team has completed exterior finish installation at Petsmart. Inside, we are completing the interior furring of the exterior walls with insulation.

We have framed the exterior soffits at Michaels and clad them with plywood. Wall furring is complete, along with electrical, plumbing and framing inspection. Our team is progressing with ductwork, electrical rough-in and wall framing.

We are erecting tilt-up panels at Ross Dress for Less, TJ Maxx and several other retail shops. Masonry work is also progressing at various points around the site. Site flume concrete excavation is in progress.