PetSmart Punch List in Progress

Pooler Collage 1Pooler Collage 2

It’s been a pleasure to watch our work come together this week. The punchlist is in progress at PetSmart and cash wraps and fish tanks are in place.

Thin brick installation is in progress at Michael’s and interior stairs have been painted. At Ross Dress for Less,¬†EIFS and thin brick installation is in progress. Lights have been installed on the sales floor, and a light valence backing has been installed and painted.

Around the rest of the site, EIFS is progressed, along with interior framing and drywall installation. We are now grading the last area of parking lot, where the construction trailer was sitting. Parking lot signage is being mounted.