Foundations Built for Monument Signage

Pooler Collage 2Pooler Collage 12-20-13

Onsite, our crews are busy completing work at the major retailers and framing at many future retail spots.

  • Petsmart is getting the finishing touches. Exterior signage has been installed and interior fixtures are being placed.
  • Michael’s electrical panel is now in progress. EIFS is complete, as well as exterior stairs, the gas meter and bollards.
  • Ross Dress for Less now has completed EIFS. Our team installed the interior grid, and sales floor lighting is in progress.
  • T.J. Maxx crews are installing spiral duct, EIFS and framing back of house walls continues.
  • Hibbett Sports and Rack Room Shoes are seeing interior progress as well.

We completed paving in the parking lot, and striping is in progress. Foundations for signage are in progress.