Nightfall in Pooler: Many Stores are Open

Pooler CollageAs we near project close, several major retailers are open for business, including PetSmart, Kirkland’s, Hibbett and Rack Room Shoes. We anticipate that Michael’s will open on the 30th of this month, with T.J. Maxx following on April 27th and Ross Dress for Less in July. 

Petsmart/Kirklands Are Open

Pooler Collage 1 Pooler Collage 2

This week, we are really seeing the project come together. Petsmart and Kirkland’s are open for business, and final punch lists for Michaels, Ross and T.J. Maxx are  being worked through. Hibbets and Rack Room have almost completed their tenant finishes.

In Shops 1,  contractors for Kay’s Jewelers,  Palm Beach Tan, GameStop and GNC have started their build out.We are still waiting on permit for vanilla box in suite E.

In Shops 2, contractors for Legacy Nails, Sprint, Marble Slab Creamery and B&G Burgers are starting their build outs.  We have completed the Pad B building, and contractors for Aspen Dental and Vision Eyecare have started their build outs.  All paving and landscaping has been completed.

Buildouts Progressing Nicely

Pooler Collage 1Pooler Collage 2

We’ve made quite a bit of progress and clean up over the weekend, the Village on Pooler Parkway is getting closer to its final incarnation. PetSmart is the closest store to completion; They are now stocking shelves.

At Michael’s and Ross Dress for Less and T.J. Maxx, our crews have completed exterior paint, and thin brick grouting/cleaning is in progress. Retail shops4, 5 & 6, now have EIFS complete and exterior lights installed. Interior space is starting to shape up.

Elsewhere around the site, buildouts are progressing nicely. The Public Works punch list is being addressed, and paving and landscaping are moving ahead.

 

PetSmart Punch List in Progress

Pooler Collage 1Pooler Collage 2

It’s been a pleasure to watch our work come together this week. The punchlist is in progress at PetSmart and cash wraps and fish tanks are in place.

Thin brick installation is in progress at Michael’s and interior stairs have been painted. At Ross Dress for Less, EIFS and thin brick installation is in progress. Lights have been installed on the sales floor, and a light valence backing has been installed and painted.

Around the rest of the site, EIFS is progressed, along with interior framing and drywall installation. We are now grading the last area of parking lot, where the construction trailer was sitting. Parking lot signage is being mounted.

Site Upgrades in Progress: Trees, Sod and Sidewalks

Pooler Collage

At PetSmart, our team has installed metal parapet cap, and front exterior paint is complete. Floor polishing is in progress, and the pet washing area is getting wall tile, painting and ceiling grid. Exterior EIFS is progressing nicely at Michael’s, along with installation of FRP panels, auto doors and glazing at the entry vestibule. Crews at Ross Dress for Less have made great progress on EIFS, MEP and back of house framing.

Elsewhere on site, we’re seeing progress with plywood cladding, MEP and exterior sidewalks. Trees and bushes have been placed and are ready for planting, while the subgrade has been prepped for asphalt.

We’ve got Paint!

Pooler Collage 1Pooler collage 2

Week by week, we are seeing The Village on Pooler Parkway take shape. At Petsmart and Michael’s, exterior paint and interior tile work are in progress. Exterior fascia framing and cladding are complete at Ross Dress for Less, and MEP and interior wall framing are moving along. Structural steel and decking are almost complete at TJ Maxx. Exterior soffit work will start Monday.

At other locations around the site, we are seeing sidewalks poured and storefronts installed, along with additional MEP work. Irrigation systems, trees and sod have been installed on the west and north sides of the site.