Petsmart Taking Shape

At Petsmart, our team is working hard on exterior framing, roof drains and electrical rough-ins. We moved forward with Michaels steel erection, and all the slab leaveouts have been poured. The pouring and erection of walls and dock walls has been a primary task at Ross Dress for Less. We poured the slab for TJ Maxx and started tilt up panel layout. Sitework continues around the property.

Pooler Collage 1

 

Walls Rising on Site

Pooler Collage 2Pooler Collage 1

Onsite this week, our team has completed the underground fire inspection tie in. Michaels panels have been erected and block work is in progress or complete in several areas. All footers have been poured on Shops 2.

The underground plumbing is complete on Petsmart and is in progress on Shops 1 and Shops 2. Metal stud framing has started on the exterior of Petsmart and roofing is complete on Petsmart. All water meter vaults have been installed on site and the installation of the grease traps is still in progress.

Georgia Power Onsite

Pooler Collage 1Pooler Collage 2

Onsite in Pooler, Georgia Power has started installing underground cabling. Our team is starting to install the precast light poles.

Pad B block work has started, and the Outparcel 1-A pad is to now grade. Water line tie in is in progress. Columns, joists and deck has been installed on Petsmart and panel forming has started on Ross. The water meter vaults and grease trap vaults have been delivered to the site.

Site Takes Shape

Pooler Collage 1Pooler Collage 2

Onsite, curb and gutter is continuing. Our team moved ahead with Michaels panel forming, getting half of the panels poured. Joists delivered and we are ready for erection on Petsmart. Block was delivered for placement on the Pad B building, and grading work is continuing on outparcel 1-A. Sewer, storm and water line connections are in progress.

Pooler Public Works Gives Us Approval

Pooler Collage 1Pooler Collage 2

This week, our team moved forward by pouring slabs and Ross and “Shops 1.” We excavated the truck dock at Michael’s and started footings at the “Pad B” shell. The main sewer line for the site has been tied to the public sewer line.  We have received approval from Pooler Public Works Deptartment to start work on outparcel 1-A and erosion control measures. Installation is in progress.