Site Upgrades in Progress: Trees, Sod and Sidewalks

Pooler Collage

At PetSmart, our team has installed metal parapet cap, and front exterior paint is complete. Floor polishing is in progress, and the pet washing area is getting wall tile, painting and ceiling grid. Exterior EIFS is progressing nicely at Michael’s, along with installation of FRP panels, auto doors and glazing at the entry vestibule. Crews at Ross Dress for Less have made great progress on EIFS, MEP and back of house framing.

Elsewhere on site, we’re seeing progress with plywood cladding, MEP and exterior sidewalks. Trees and bushes have been placed and are ready for planting, while the subgrade has been prepped for asphalt.

We’ve got Paint!

Pooler Collage 1Pooler collage 2

Week by week, we are seeing The Village on Pooler Parkway take shape. At Petsmart and Michael’s, exterior paint and interior tile work are in progress. Exterior fascia framing and cladding are complete at Ross Dress for Less, and MEP and interior wall framing are moving along. Structural steel and decking are almost complete at TJ Maxx. Exterior soffit work will start Monday.

At other locations around the site, we are seeing sidewalks poured and storefronts installed, along with additional MEP work. Irrigation systems, trees and sod have been installed on the west and north sides of the site.

Interior Work in Progress

Pooler Collage 1Pooler Collage 2

Around the Village on Pooler Parkway, we’re seeing great progress both inside and outside the structures. At Petsmart, our team has installed storefront and auto doors, and is working on drywall tape and fill in progress. Electrical transformer and panel installation is in progress. Inside Michael’s, crews are starting to paint on the sales floor. The conveyor has been delivered and is ready for installation.

Exterior parapet forming is in progress at Ross Dress for Less, along with hurricane shutter door installation, interior framing and MEP rough-in. Down the way at T.J. Maxx, all tilt panels have been erected, and our team began excavation for the loading dock. Backfill of tilt up walls is moving along nicely.

Elsewhere onsite, ongoing activities include fascia and soffit framing, interior framing, installation of underground plumbing, light gauge framing, curb and gutter and decking steel structure.

Ready for Landscaping

Pooler Collage 1Pooler Collage 2

We’ve been busier than ever at The Village on Pooler Parkway, watching the site take more shape. At Petsmart & Michaels, interior framing and drywall installation is in progress. Our team has completed steel erection at Ross, and roofing installation is moving ahead. Buildings 4-5-6 are in the steel erection phase as well.

The underslab plumbing has been installed and inspected on Outparcel 1-A building. The installation gas line to the site and to each space is in progress. Landscaping is starting today.

Tilt-Up Walls Continue to Rise

Pooler Collage 10-4-13

Work is progressing nicely across the entire site on Pooler Parkway. Our team has completed exterior finish installation at Petsmart. Inside, we are completing the interior furring of the exterior walls with insulation.

We have framed the exterior soffits at Michaels and clad them with plywood. Wall furring is complete, along with electrical, plumbing and framing inspection. Our team is progressing with ductwork, electrical rough-in and wall framing.

We are erecting tilt-up panels at Ross Dress for Less, TJ Maxx and several other retail shops. Masonry work is also progressing at various points around the site. Site flume concrete excavation is in progress.

Light Pole Installation Begins

Pooler Collage 1 Pooler Collage 2

Around the site this week, our team made progress with block wall installation. Curb and gutter work is progressing, along with light pole installation. At the anchor stores, we have the following updates:

  • PetSmart: We are installing exterior soffit framing with plywood cladding and wood parapet caps.
  • Michael’s: Exterior steel installation and parapet framing are moving along.
  • Ross Dress for Less: Panels have been poured and all form material has been cleaned.
  • TJ Maxx: Our team is moving ahead with panel forming, rebar placement and embed placement.